Phase 3

Our deck crew will come in and pour your deck or install pavers around your pool area. The coping and tile of the 
pool are completed in the next step.
Pool equipment and electrical are installed. Our team will teach you how to run and operate your pool system.  
We are always available to answer any questions you might have for the future of your pool.


How long does it take?

An average pool is built in 30 - 40 days, from the release of permit.

Phase 1

Once the permit is pulled we will layout the pool structure. Then excavation will take place. Excavation 
is typically completed in one day for an average sized pool. Steel rebar is then laid to create a reinforcement
for the concrete shell of the swimming pool. 

 “Allen was honest and his team did a great job. Allen and his family stayed involved in the entire job from beginning to end. We are looking forward to a long term relationship with this company, we will be using them not only to service our newly remodeled pool but in all of our future renovations. Can't say enough good things about Independent Pool. Thanks Again!" Charles and Family.

​ -Charles and family

 Your friendly neighborhood Pool Builder in the Venice area!  Samantha and Allen are great folks. We are super happy that we met them.  Finally we have a new go to person for all of our pool needs!  Keep up the good work guys!"

​ -Jessica parker

 “"I sent Allen a text and he responded very quickly with a return call. He was able to come out the next day and install a new motor on my filter. There were no hidden charges, no games, no problems. He did a great job and I will be his number for any further pool issues that I may encounter in the future. Thanks Allen!"

​ -Cathy Moseley

Learn More

About Construction

 Phase 4

If the homeowner has chosen a pool cage or fence this will be the next step. The pool is almost complete! Our finish crew will come in and apply the selected pool finish, after the shell has been acid washed. We will clean up any construction debris and balance the swimming pool. Professional chemical balancing is crucial in the first 30 days of your new pool construction or renovation.​

Phase 2

Concrete is then shot into the swimming pool in a process called "shotcrete" application. We believe in using
high quality material to build swimming pools, so that homeowner's do not run into costly inconveniences in the future
The rough plumbing layout is next, following inspection from the county.